| Project Name: Hectares BC | Project Manager: Anne Downton
|
| Reporting Period: Week of 07-Jan-08 | Today's Date: 10-Jan-08
|
Budget Summary
* Have spent $119,500 to date
Summary - Nature Trust Contract
| Status | Status Summary
|
| No | 1. Has the scope changed or is it about to be impacted?
|
| No | 2. Have the deliverables/objectives changed?
|
| No | 3. Are there sponsorship/stakeholder issues?
|
| No | 4. Are there new risks?
|
| No | 5. Are there productivity problems affecting the team's ability to perform the work?
|
| No | 6. Are there resourcing problems?
|
| No | 7. Is a deliverable/milestone about to be missed?
|
| No | 8. Has the estimated schedule changed?
|
| No | 9. Is the quality of the deliverables being affected?
|
| No | 10. Have the estimated costs (i.e. out of pocket) changed?
|
| No | 11. Will the benefits not be realized?
|
| Yes | 12. Are there any other major issues?
|
Explanation of "Yes" items
| Contract | We have drafted a contract and are waiting to hear back from The Nature Trust.
|
| Issue | Status | Summary and Description
|
| none at this time | |
|
Deliverable Status - Nature Trust Contract
[-May 15, 2007 - October 15, 2007-]
| | Completion Dates | | |
|
| Deliverable/Milestone | Target Date | Estimated | Revised | Actual | Current Status
|
| Project Charter | May 28, 2007 | | | June 15, 2007 | Complete
|
| List of Stakeholders | May 30, 2007 | | | June 12, 2007 | Complete
|
| User Stories | Sept 14, 2007 | Sept 4, 2007 | | Sept 4, 2007 | Complete
|
| Requirements Specification | July 24, 2007 | Sept 6, 2007 | | Sept 6, 2007 | Complete
|
| Data Layers | July 24, 2007 | Oct 15, 2007 | | Oct 9,2007 | Complete - but ongoing
|
| UI Design Specification: Workflow and Screen Design | Sept 26, 2007 | Sept 6, 2007 | | Sept 6, 2007 | Complete
|
| Design Specification: Architecture Design | Sept 06, 2007 | Sept 30, 2007 | | Sept 28, 2007 | Complete
|
Explanation of Deliverable Status
The above deliverables list will be updated once the contract is signed.
Deliverable Status - Geoconnections
| | Completion Dates | | |
|
| Deliverable/Milestone | Due | Revised | Actual | Current Status
|
| Project Charter | July 16, 2007 | | June 15, 2007 | Complete
|
| Requirements Document | July 16, 2007 | Sept 6, 2007 | Sept 6, 2007 | Complete
|
| Use Case Document/User Stories | July 16, 2007 | Sept 4, 2007 | Sept 4, 2007 | Complete
|
| Design and Architecture Document | July 16, 2007 | Sept 30, 2007 | Sept 28, 2007 | Complete
|
| Milestone Report 1 | July 16, 2007 | | | Complete
|
| Infrastructure and Development Environment Document | Nov 16, 2007 | | Nov 5, 2007 | Complete
|
| Milestone Report 2 | Nov 16, 2007 | | | Complete
|
| Modules Document | Mar 31, 2007 | | |
|
| Milestone Report 3 | Mar 31, 2007 | | |
|
| Preliminary Provincial Inventories | June 27, 2008 | | |
|
| User Acceptance Test Plan | June 27, 2008 | | |
|
| User Documentation | June 27, 2008 | | |
|
| Register Services with Discovery Portal | June 27, 2008 | | |
|
| Milestone Report 4 | June 27, 2008 | | |
|
| Final Report | June 27, 2008 | | |
|