Back to HabcStatusReports


Project Name: Hectares BCProject Manager: Anne Downton
Reporting Period: Week of 07-Jan-08Today's Date: 10-Jan-08

Budget Summary

* Have spent $119,500 to date

Summary - Nature Trust Contract

Status Status Summary
No 1. Has the scope changed or is it about to be impacted?
No 2. Have the deliverables/objectives changed?
No 3. Are there sponsorship/stakeholder issues?
No 4. Are there new risks?
No 5. Are there productivity problems affecting the team's ability to perform the work?
No 6. Are there resourcing problems?
No 7. Is a deliverable/milestone about to be missed?
No 8. Has the estimated schedule changed?
No 9. Is the quality of the deliverables being affected?
No 10. Have the estimated costs (i.e. out of pocket) changed?
No 11. Will the benefits not be realized?
Yes 12. Are there any other major issues?

Explanation of "Yes" items

ContractWe have drafted a contract and are waiting to hear back from The Nature Trust.

Input Required from Matt Austin, Project Manager MOE

Issue Status Summary and Description
none at this time

Explanation of input required


Deliverable Status - Nature Trust Contract

[-May 15, 2007 - October 15, 2007-]

Completion Dates
Deliverable/Milestone Target Date Estimated Revised Actual Current Status
Project CharterMay 28, 2007 June 15, 2007Complete
List of StakeholdersMay 30, 2007 June 12, 2007Complete
User StoriesSept 14, 2007Sept 4, 2007 Sept 4, 2007Complete
Requirements SpecificationJuly 24, 2007Sept 6, 2007 Sept 6, 2007 Complete
Data LayersJuly 24, 2007Oct 15, 2007 Oct 9,2007Complete - but ongoing
UI Design Specification: Workflow and Screen DesignSept 26, 2007Sept 6, 2007 Sept 6, 2007Complete
Design Specification: Architecture DesignSept 06, 2007Sept 30, 2007 Sept 28, 2007 Complete

Explanation of Deliverable Status

The above deliverables list will be updated once the contract is signed.

Deliverable Status - Geoconnections

Completion Dates
Deliverable/Milestone Due Revised Actual Current Status
Project CharterJuly 16, 2007 June 15, 2007Complete
Requirements DocumentJuly 16, 2007Sept 6, 2007Sept 6, 2007Complete
Use Case Document/User StoriesJuly 16, 2007Sept 4, 2007Sept 4, 2007Complete
Design and Architecture DocumentJuly 16, 2007Sept 30, 2007Sept 28, 2007Complete
Milestone Report 1July 16, 2007 Complete
Infrastructure and Development Environment DocumentNov 16, 2007 Nov 5, 2007Complete
Milestone Report 2Nov 16, 2007 Complete
Modules DocumentMar 31, 2007
Milestone Report 3Mar 31, 2007
Preliminary Provincial InventoriesJune 27, 2008
User Acceptance Test PlanJune 27, 2008
User DocumentationJune 27, 2008
Register Services with Discovery PortalJune 27, 2008
Milestone Report 4June 27, 2008
Final ReportJune 27, 2008