Back to HabcStatusReports


Current Status Report


Project Name: Hectares BCProject Manager: Jeff Lounsbury
Reporting Period: up to 06-June-08Today's Date: 09-June-08

Budget Summary

* Have spent $251,000 to date

* Have spent $262,500 (including GST) to date

* Total spent on Biodiversity Analysis = $3,050

* Budget remaining: $500, including the $3k from biodiversity work for 262k total. (Amended Contract of $260,000 total, including GST)

Summary - Nature Trust Contract

Status Status Summary
No 1. Has the scope changed or is it about to be impacted?
No 2. Have the deliverables/objectives changed?
No 3. Are there sponsorship/stakeholder issues?
No 4. Are there new risks?
No 5. Are there productivity problems affecting the team's ability to perform the work?
No 6. Are there resourcing problems?
No 7. Is a deliverable/milestone about to be missed?
No 8. Has the estimated schedule changed?
No 9. Is the quality of the deliverables being affected?
No 10. Have the estimated costs (i.e. out of pocket) changed?
No 11. Will the benefits not be realized?
No 12. Are there any other major issues?

Explanation of "Yes" items

none at this time.


Input Required from Matt Austin, Project Manager MOE

Issue Status Summary and Description
Questions regarding individual data layers will be addressed through email.

Explanation of input required

none at this time.


Services - The Nature Trust

[-May 15, 2007 - June 30, 2008-] The following documents are available on the Project Documents page

Completion Dates
Deliverable/Milestone Target Date Actual Current Status Location
Project CharterMay 28, 2007June 15, 2007Complete- Project Documents
List of StakeholdersMay 30, 2007June 12, 2007Complete- Project Team
User StoriesSept 14, 2007Sept 4, 2007Complete - but not updated- Project Documents
Requirements SpecificationJuly 24, 2007Sept 6, 2007 Complete- Project Documents
Data LayersJuly 24, 2007Oct 9,2007Complete - but ongoing- Project Documents
UI Design Specification: Workflow and Screen DesignSept 26, 2007Sept 6, 2007Complete- Project Documents
Design Specification: Architecture DesignSept 06, 2007Sept 28, 2007 Complete- Project Documents
Operating System and Development Environment SetupOct 31, 2007Nov 16, 2007Complete- Project Documents
Infrastructure and Development Standards DocumentNov 16, 2007Nov 16, 2007Complete- Project Documents
Map Viewer ModuleNov 17, 2007Oct 22, 2007Complete- Project Documents
Real-time Query ModuleNov 17, 2007Jan 15, 2008Complete- Project Documents
Modules DocumentationNov 16, 2007Nov 16, 2007Complete - but ongoing- Project Documents
Metadata Infrastructure ModuleJan 15, 2008Jan 15, 2008Complete- Project Documents
Query Builder: Equation Editor and Manager ModuleJan 15, 2008Jan 15, 2008Complete- Project Documents
Data Loading Phase 1Jan 15, 2008Jan 15, 2007Complete (except VRI data)In application
Raw Data Access: WCS InterfaceJan 15, 2008Jan 15, 2008Complete- Project Documents
Batch Data Summerizer ModuleFeb 14, 2008 Not CompleteWill not be completing 2 batch controllers as originally planned - see item below due May 12
Data Loading Infrastructure ModuleMar 13, 2008 In ProgressSee Technical Documentation (due March 31/08)
Data Loading Phase 2Mar 13, 2008March 12, 2008CompleteIn application
Revised Module DocumentationMar 31, 2008 March 18, 2008 Complete- Project Documents
Log in ModuleApr 11, 2008 April 8, 2008 Complete In application
Batch Controller ModuleMay 12, 2008 April 8, 2008 Complete In application
User Acceptance Test PlanMay 12, 2008 May 20 Complete
Load Provincial InventoriesMay 12, 2008 n/a Complete In Application
User Acceptance TestingJune 10, 2008
Register with Discovery PortalJune 27, 2008
Migration StrategyJune 27, 2008 Complete
User DocumentationJune 27, 2008 Complete
Revised Module DocumentationJune 28, 2008 Complete

Explanation of Deliverable Status

none at this time.

Deliverables - The Nature Trust

Completion Dates
Deliverable/Milestone Due Revised Actual Current Status
Project CharterJuly 16, 2007 June 15, 2007Complete
Requirements DocumentJuly 16, 2007Sept 6, 2007Sept 6, 2007Complete
Use Case Document/User StoriesJuly 16, 2007Sept 4, 2007Sept 4, 2007Complete
Design and Architecture DocumentJuly 16, 2007Sept 30, 2007Sept 28, 2007Complete
Milestone Report 1July 16, 2007 Complete
Infrastructure and Development Environment DocumentNov 16, 2007 Nov 5, 2007Complete
Milestone Report 2Nov 16, 2007 Complete
Modules DocumentMar 31, 2007 March 18, 2008Complete
Milestone Report 3Mar 31, 2007 In progress
Preliminary Provincial InventoriesJune 27, 2008 Complete
User Acceptance Test PlanJune 27, 2008 Complete
User DocumentationJune 27, 2008 Complete
Register Services with Discovery PortalJune 27, 2008
Milestone Report 4June 27, 2008
Final ReportJune 27, 2008