| | 5 | = Current Status Report = |
|---|
| | 6 | ---- |
|---|
| | 7 | ||'''Project Name:''' Hectares BC||'''Project Manager:''' Jeff Lounsbury|| |
|---|
| | 8 | ||'''Reporting Period:''' up to 21-Mar-08||'''Today's Date:''' 25-Mar-08|| |
|---|
| | 9 | ---- |
|---|
| | 10 | == Budget Summary == |
|---|
| | 11 | * Have spent $197,000 to date |
|---|
| | 12 | |
|---|
| | 13 | * Have spent $206,000 (including GST) to date |
|---|
| | 14 | |
|---|
| | 15 | * Total spent on Biodiversity Analysis = $3,050 |
|---|
| | 16 | |
|---|
| | 17 | * Budget remaining $33,000 |
|---|
| | 18 | |
|---|
| | 19 | == Summary - Nature Trust Contract == |
|---|
| | 20 | || '''Status''' ||'''Status Summary'''|| |
|---|
| | 21 | || No ||1. Has the scope changed or is it about to be impacted?|| |
|---|
| | 22 | || No ||2. Have the deliverables/objectives changed?|| |
|---|
| | 23 | || No ||3. Are there sponsorship/stakeholder issues?|| |
|---|
| | 24 | || No ||4. Are there new risks?|| |
|---|
| | 25 | || No ||5. Are there productivity problems affecting the team's ability to perform the work?|| |
|---|
| | 26 | || No ||6. Are there resourcing problems?|| |
|---|
| | 27 | || No ||7. Is a deliverable/milestone about to be missed?|| |
|---|
| | 28 | || No ||8. Has the estimated schedule changed?|| |
|---|
| | 29 | || No ||9. Is the quality of the deliverables being affected?|| |
|---|
| | 30 | || No ||10. Have the estimated costs (i.e. out of pocket) changed?|| |
|---|
| | 31 | || No ||11. Will the benefits not be realized?|| |
|---|
| | 32 | || No ||12. Are there any other major issues?|| |
|---|
| | 33 | |
|---|
| | 34 | === Explanation of "Yes" items === |
|---|
| | 35 | none at this time. |
|---|
| | 36 | ---- |
|---|
| | 37 | |
|---|
| | 38 | === Input Required from Matt Austin, Project Manager MOE === |
|---|
| | 39 | || '''Issue''' || '''Status''' ||'''Summary and Description''' || |
|---|
| | 40 | ||Questions regarding individual data layers will be addressed through email.|| || || |
|---|
| | 41 | |
|---|
| | 42 | === Explanation of input required === |
|---|
| | 43 | none at this time. |
|---|
| | 44 | ---- |
|---|
| | 45 | |
|---|
| | 46 | == Services - The Nature Trust == |
|---|
| | 47 | [-May 15, 2007 - June 30, 2008-] |
|---|
| | 48 | The following documents are available on the Project Documents page |
|---|
| | 49 | |
|---|
| | 50 | || || '''Completion Dates''' |||||||| |
|---|
| | 51 | || '''Deliverable/Milestone''' || '''Target Date''' || '''Actual''' || '''Current Status''' || '''Location''' || |
|---|
| | 52 | ||Project Charter||May 28, 2007||June 15, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 53 | ||List of Stakeholders||May 30, 2007||June 12, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectTeam - Project Team]|| |
|---|
| | 54 | ||User Stories||Sept 14, 2007||Sept 4, 2007||Complete - but not updated||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 55 | ||Requirements Specification||July 24, 2007||Sept 6, 2007 ||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 56 | ||Data Layers||July 24, 2007||Oct 9,2007||Complete - but ongoing||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 57 | ||UI Design Specification: Workflow and Screen Design||Sept 26, 2007||Sept 6, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 58 | ||Design Specification: Architecture Design||Sept 06, 2007||Sept 28, 2007 ||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 59 | ||Operating System and Development Environment Setup||Oct 31, 2007||Nov 16, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 60 | ||Infrastructure and Development Standards Document||Nov 16, 2007||Nov 16, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 61 | ||Map Viewer Module||Nov 17, 2007||Oct 22, 2007||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 62 | ||Real-time Query Module||Nov 17, 2007||Jan 15, 2008||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 63 | ||Modules Documentation||Nov 16, 2007||Nov 16, 2007||Complete - but ongoing||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 64 | ||Metadata Infrastructure Module||Jan 15, 2008||Jan 15, 2008||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 65 | ||Query Builder: Equation Editor and Manager Module||Jan 15, 2008||Jan 15, 2008||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 66 | ||Data Loading Phase 1||Jan 15, 2008||Jan 15, 2007||Complete (except VRI data)||In application|| |
|---|
| | 67 | ||Raw Data Access: WCS Interface||Jan 15, 2008||Jan 15, 2008||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 68 | ||Batch Data Summerizer Module||Feb 14, 2008|| ||Not Complete||Will not be completing 2 batch controllers as originally planned - see item below due May 12|| |
|---|
| | 69 | ||Data Loading Infrastructure Module||Mar 13, 2008|| ||In Progress||See Technical Documentation (due March 31/08)|| |
|---|
| | 70 | ||Data Loading Phase 2||Mar 13, 2008||March 12, 2008||Complete||In application|| |
|---|
| | 71 | ||Revised Module Documentation||Mar 31, 2008|| March 18, 2008 ||Complete||[http://habc.refractions.net/trac/wiki/HabcProjectDocuments - Project Documents]|| |
|---|
| | 72 | ||Log in Module||Apr 11, 2008|| || || |
|---|
| | 73 | ||Batch Controller Module||May 12, 2008|| || || |
|---|
| | 74 | ||User Acceptance Test Plan||May 12, 2008|| || || |
|---|
| | 75 | ||Load Provincial Inventories||May 12, 2008|| || || |
|---|
| | 76 | ||User Acceptance Testing||June 10, 2008|| || || |
|---|
| | 77 | ||Register with Discovery Portal||June 27, 2008|| || || |
|---|
| | 78 | ||Migration Strategy||June 27, 2008|| || || |
|---|
| | 79 | ||User Documentation||June 27, 2008|| || || |
|---|
| | 80 | ||Revised Module Documentation||June 28, 2008|| || || |
|---|
| | 81 | |
|---|
| | 82 | |
|---|
| | 83 | ----- |
|---|
| | 84 | |
|---|
| | 85 | === Explanation of Deliverable Status === |
|---|
| | 86 | none at this time. |
|---|
| | 87 | |
|---|
| | 88 | |
|---|
| | 89 | == Deliverables - The Nature Trust == |
|---|
| | 90 | |
|---|
| | 91 | || || '''Completion Dates''' |||||| || |
|---|
| | 92 | || '''Deliverable/Milestone''' || '''Due''' || '''Revised''' || '''Actual''' || '''Current Status''' || |
|---|
| | 93 | ||Project Charter||July 16, 2007|| ||June 15, 2007||Complete|| |
|---|
| | 94 | ||Requirements Document||July 16, 2007||Sept 6, 2007||Sept 6, 2007||Complete|| |
|---|
| | 95 | ||Use Case Document/User Stories||July 16, 2007||Sept 4, 2007||Sept 4, 2007||Complete|| |
|---|
| | 96 | ||Design and Architecture Document||July 16, 2007||Sept 30, 2007||Sept 28, 2007||Complete|| |
|---|
| | 97 | ||Milestone Report 1||July 16, 2007|| || ||Complete|| |
|---|
| | 98 | ||Infrastructure and Development Environment Document||Nov 16, 2007|| ||Nov 5, 2007||Complete|| |
|---|
| | 99 | ||Milestone Report 2||Nov 16, 2007|| || ||Complete|| |
|---|
| | 100 | ||Modules Document||Mar 31, 2007|| ||March 18, 2008||Complete|| |
|---|
| | 101 | ||Milestone Report 3||Mar 31, 2007|| || ||In progress|| |
|---|
| | 102 | ||Preliminary Provincial Inventories||June 27, 2008|| || || || |
|---|
| | 103 | ||User Acceptance Test Plan||June 27, 2008|| || || || |
|---|
| | 104 | ||User Documentation||June 27, 2008|| || || || |
|---|
| | 105 | ||Register Services with Discovery Portal||June 27, 2008|| || || || |
|---|
| | 106 | ||Milestone Report 4||June 27, 2008|| || || || |
|---|
| | 107 | ||Final Report||June 27, 2008|| || || || |