Working Group Meeting

October 2, 2007

Attending:Greg LawranceMatt Austin
Adrian WaltonPaul RamseyEmily Gouge
Amr AlamAnne Downton

Agenda

Introductions

  • Amr is a new developer on the team

Geoconnections Milestone Report #1

  • Financial Statement

Goals of Sprint #1

  • Submit server specs
  • Establish temporary server at RRI
  • Document Software, version and standards on the wiki
  • Complete first draft of Systems Document
  • View a list of data layers

Demonstration of functionality developed during Sprint #1 (Sept 7-21)

Goals of the current Sprint #2 (Sept 21 - Oct 22)

  • Submit systems doc
  • Have a working base map
  • Implement logging system (Error Handling)
  • View a default base map
  • Drag a layer into the query definition window
  • View map results for a single layer
  • Zoom and pan around map

Update on the layers list in sharepoint

Server