     4== Sprint !#2 == 
     5Sept 21 - Oct 22 
     6 
     7=== Goals === 
     8 * submit systems doc to Matt 
     9 * working base map 
     10 * complete logging system 
     11 * view map results for a single layer 
     12 * zoom and pan around 
     13 * drag a layer into the definition window 
     14 
     15[[Image(sprint2.png)]] 
     16 
     17=== Retrospective === 
     18[-the good-] 
     19 * Everyone buys into the scrum process 
     20 * We did what we set out to do 
     21 
     22[-the bad-] 
     23 * The last week of the sprint was disorganized 
     24 * Not enough tasks were broken down; we should spend a bit more time breaking down tasks in the midsprint review 
     25 * We overestimated how long it would take us to complete tasks, which left us with fewer things done than what we would have otherwise accomplished. 
     26 * IE sucks 
     27 * I feel continuously interrupted and times and totally unproductive 
     28 
     29[-for next sprint-] 
     30 
     31Based on the feedback from the sprint retrospective, we will do the following during Sprint 3: 
     32 * Spend more time at the midsprint review decomposing tasks so that if we are moving quickly through tasks, there are options in the uncommitted backlog to pull over to the current sprint. 
     33 * Allocate time to investigating and dealing with inconsistencies between browsers 
     34 * Before we ask someone on the team a question, we should ask ourselves if it's something that needs to be addressed immediately, or can it wait until that person appears to be interrupted or distracted.